Assembly Procedure 2 |
|
|
|
Trunnion, Hub and Girder |
|
|
|
Hub fitted into Girder |
|
|
|
Trunnion fitted into Hub-Girder |
|
|
|
Completed THG assembly |
|
Hub in Girder Assembly |
|
The hub is lowered into the liquid nitrogen dewar*
|
|
The hub is taken out of the liquid nitrogen dewar after the hub reaches a temperature of below -315 F
|
|
The cold hub is being lowered into the girder hole. The hub is shrink fit into the girder to give the hub-girder assembly
|
|
Trunnion in Hub-Girder Assembly |
|
Heating Blankets were used to raise the temperature of the hub-girder to 200 F |
|
The cooled trunnion is taken out of the liquid nitrogen dewar to be shrink fit into the hub-girder assembly
|
|
At steady state, the whole trunnion-hub-girder assembly was raised to show the shrink fit. |